The Federal Government has given a timeline for the completion of the Apapa-Oshodi-Ojota-Oworonsoki expressway project.
The government said the reconstruction/rehabilitation of the expressway which was inaugurated by President Muhammadu Buhari in November 2018, to resolve the Apapa traffic gridlock, will be completed within 9 to 10 months.
This disclosure was made by the Federal Controller of Works in Lagos, Mr Olukayode Popoola, during a joint inspection with the Nigerian Ports Authority (NPA) on Saturday, April 17, 2021.
READ: FG explains why Lagos-Ibadan rail line was not linked to the sea
He assured that section one of the project would be completed within 3 weeks and thereafter opened for use.
Popoola said that the rehabilitation works, which had been divided into four sections to ease port congestion and gridlock at the Apapa axis, have section one which spans from Liverpool Round through Creek Road to Beachland near Sunrise and is about 10 km, while section two is 8.4 km and spans from Beachland to Cele Bus Stop.
Briefing the press after the inspection that also had in attendance the NPA Managing Director, Hadiza Usman, and the Hitech Construction Company, the subcontractor handling the project on behalf of the Dangote Group, Popoola said that grey areas such as accessibility due to trucks infringing on construction zone and disagreements on the pace of construction had been resolved.
READ: FG to distribute 10 million LPG gas cylinders in 1 year
What the Federal Controller of Works in Lagos is saying
Popoola said that the inspection gave the NPA team the opportunity to see for themselves that the contractor had been working progressively.
He said, “And this section that we are is the end of section one which we have completed. We will complete the remaining portion within the next three weeks, especially the asphalt work.
So within that three weeks, the outstanding works will be completed fully and then the section one will be made available to the motorists.
We (FMW) also complained about the trucks that are infiltrating the road while we are working. We have told them (NPA) that we cannot allow trucks to flock onto the section where we are working because they will disturb the contractor.
READ: Nigeria’s Untapped LPG Market: Where Policy and Investment Meet
So the trucks will now be monitored and controlled fully. Both the NPA security, the Nigerian Police, LASTMA and then the contractor’s representative will form a synergy to work out how they will be controlling the trucks that enter into the port road henceforth,’’ Popoola said.
He said the contractor is expected to move to site to start the construction works on section two of the project based on agreement adding that work on sections three and four had reached an advanced stage, with over 70% completion reached cumulatively.
Popoola said that the entire project would be completed and handed over within the next nine to 10 months, including section two which had just been awarded.
READ: Fuel subsidy: To be or not to be?
The NPA Managing Director said that agreements were reached on timelines for construction works in order not to disrupt port operations with resolutions that the contractor worked during the weekends and on public holidays to ease congestion.
She said it was resolved that a corridor would be opened for trucks movement in addition to palliative works on some roads and another inspection in three weeks on section one.
The contract was awarded to AG Dangote Construction Company Ltd at the cost of N73bn under the Tax Credit Scheme of the Federal Government.
What you should know
- It can be recalled that the Federal Government had earlier in the year said that the first phase of the Apapa-Oshodi-Ojota-Oworonshoki project, which has faced several delays, would be delivered in April 2021.
- The government said that sections one, three and four of the project which was awarded to AG Dangote Construction Company Ltd at the cost of N73bn under the Tax Credit Scheme of the Federal Government, were almost ready and would be completed in April.
- They had also said that section two of the project which spans from Beach Land bus stop area to Cele Bus Stop which was recently awarded would also be completed in December 2021.