Site icon Nairametrics

Explainer: The 188MW Geometric Power Plant and its impact on Aba residents

The inauguration of the 188MW Geometric Power Plant in Aba, Abia State, marks a pivotal development, poised to significantly alter the energy narrative for its residents.

This development is not just a milestone for Aba but a beacon of progress for Nigeria’s broader electricity challenges, characterized by issues in power generation, transmission, and distribution.

To comprehend the significance of this power plant, it is essential to contextualize its impact on the current power dynamics and the challenges that lie ahead.

A short history of the plant

The Geometric Power Plant initiative was conceived as far back as 2004 before the power sector reforms were fully implemented. Work started about 4 years later. The first phase of the project was completed around 2013.

The second turbine will come on stream once the performance of the first turbine is declared satisfactory by the team of engineers led by KSE Energy of Turkey and Engineer Ben Caven, a former executive director of the National Electric Power Authority (NEPA), reputed to be the only person to have run the generation, engineering, and transmission divisions of the state-owned utility.

Understanding the Power Dynamics

The size of the Geometric Power Plant is impressive for the Aba ring-fenced coverage area. For example, Lagos State, one of Nigeria’s most industrialized regions, generates about 800-1000MW of electricity monthly, despite a demand estimated at 2000MW.

This allocation falls short of meeting the region’s energy needs, making the introduction of the Geometric Power Plant’s 188MW particularly noteworthy.

The Impact of 188MW

To grasp the magnitude of this development, a 185MW power plant operating 24/7 should generate approximately 135,360,000 kWh of electricity per month.

This plant could theoretically support around 270,00 households, assuming an average household consumption of 500kWh. Such a figure highlights the plant’s potential to considerably alleviate the energy scarcity in Abia State.

Challenges Beyond Generation

However, generating power is only part of the solution. The larger hurdles lie in the efficient transmission and distribution of this generated electricity to end-users. The success of this venture hinges on several critical factors:

Gas Supply: The power plant’s operation depends on a reliable natural gas supply. Geometric has laid a 27km pipeline for this purpose, but the sustainability of this supply is crucial.

Power Purchase Agreements (PPAs): The enforcement of PPAs between Geometric, Aba Power Ltd (APLE), and consumers will determine the stability of power distribution. These agreements are vital for ensuring that the generated power reaches its intended industrial and residential recipients.

Legacy Debts and Tariffs: Addressing the existing debts owed to Discos and establishing a cost-reflective tariff that aligns with the Nigerian Electricity Regulatory Commission (NERC) guidelines remain significant challenges. These financial intricacies will play a critical role in the plant’s operational viability.

The Promise of Reliability

Despite these challenges, there is a cautiously optimistic outlook for the provision of 24-hour power supply to Aba residents.


This article was first written as an X (formerly Twitter) Post by @ugodre. It has been adapted here as an Explainer article.

Exit mobile version